Prototype roadmap
Turn the design into a dated plan that a team can follow. Each stage has a deliverable and a gate. The plan shows the critical path and the date by which each long-lead part must be ordered. Write it to hw/roadmap.md.
Talk to the user in the user's language. Files are in English unless the user's project uses another language.
Inputs
| File | What you take from it |
|---|---|
hw/brief.md |
launch target, quantities, markets, budget |
hw/state.json |
stage reached so far, gates already passed |
hw/bom.csv |
lead_time_wk, stock_snapshot, lifecycle; custom parts (cell, molded parts, flex) |
hw/power/ |
whether the power budget is measured or only estimated |
hw/compliance.md |
certification durations and blocking items ("Schedule hooks") |
hw/cost/ |
tooling and NRE lead times, MOQs |
hw/doability/review.md |
open risks that need an experiment before a commitment |
Outputs
hw/roadmap/stages.json: stages, dependencies, duration ranges, gates, milestones and long-lead items. The format is intemplates/stages.example.json.hw/roadmap/schedule.mdandhw/roadmap/timeline.svg: generated byscripts/roadmap.py.hw/roadmap.md: the plan, built fromtemplates/roadmap.md, including the bring-up log.hw/state.json: the current stage and the next gate.
Procedure
Place the project. Decide which stage it is in: idea, Stage 0, Stage 1, EVT-n, DVT, PVT or MP. Use what has actually been built and measured. Do not use how finished the CAD looks: a collision-free 3D model means the industrial design is frozen, not the engineering.
Write the stages JSON. Start from
templates/stages.example.json, and remove the stages the product does not need. For example, a product with a catalogue cell has no custom-cell stage.- For each stage, give a
[best, worst]duration in weeks, its dependencies (depends_on, optionallag_weeks, negative for overlap) and an exit gate. Take the gates fromreferences/stages.md. - Use real lead times from
hw/bom.csv, supplier quotes andhw/compliance.mdwhere you have them. Tag each duration as verified or estimate. - Add a
long_leadentry for every part whose lead time is 12 weeks or more, or whose stock is low, with the stage that first needs it. - Give each
long_leadentryqty_neededand, when you have it, today's distributor stock:"stock": {"on_hand": 9278, "source": "LCSC", "date": "YYYY-MM-DD"}. When the order-by date from the factory lead time has passed but the stock coversqty_needed, the item is buy now from stock, not late. With too little stock or no stock data, it stays LATE and shows the shortfall. - Dependencies go in
depends_on. The script rejects unknown stage keys, so a typo such asafterfails loudly instead of silently starting the stage at week 0.
- For each stage, give a
Generate:
python3 ${CLAUDE_SKILL_DIR}/scripts/roadmap.py --stages hw/roadmap/stages.json --md hw/roadmap/schedule.md --svg hw/roadmap/timeline.svgRead the critical path, the "LATE" rows and the "in stock: buy now" rows. Look at the SVG before you embed it: stage names wrap between words, and milestone labels take separate lanes so they never cover each other. Test the script with
python3 ${CLAUDE_SKILL_DIR}/scripts/test_roadmap.py.Check the order of commitments. No custom cell, mold or board revision may start before the measurement that sizes it. If the plan has one, move it, or write down why the risk is accepted (
hw/decisions.md).- The usual critical path: power measurement → cell decision → custom cell → UN 38.3 → certification → sale.
- The final mold also waits for the cell envelope.
Write
hw/roadmap.md. The answer comes first:- where the project is now;
- the first legal sale, best and worst case, and what drives it;
- what to order now;
- the next gate.
Then give the timeline, the per-stage plans, an empty bring-up log and the schedule risks.
During EVT and later, use
references/bringup-checklist.mdfor each new board and log the results. Usereferences/test-fixtures.mdto plan test access before routing, and fixtures before PVT.Hand off.
cost-and-sourcingtakes the NRE timing and the long-lead purchases.doability-reviewtakes the stage the project is in and the uncommitted measurements.product-presentationtakestimeline.svgand the answer-first block.
Gate
The roadmap stage passes when:
- every stage has a deliverable, a duration range with an evidence tag and an exit gate;
- the critical path is identified, and no custom part starts before the measurement that sizes it (or the accepted risk is logged);
- every long-lead part has an order-by date, and late items are reported to the user;
- the first-legal-sale date is a range (best to worst), not a single optimistic date.
Taste and pitfalls
- Measure first. The first engineering deliverable is often a measurement bench, not a PCB. Current measured on a dev kit with the real duty cycle sizes the battery, the memory and the enclosure.
- The 3D model freezes the industrial design, not the engineering. Expect 3–4 board revisions and 1–2 mold iterations before mass production. Do not call a design "final" before it has been powered, measured, dropped and certified.
- Quote ranges, never single dates. Teams that promise the best case to customers end up refunding pre-orders.
- Order long-lead parts at once. Order EVT and DVT quantities as soon as a part is chosen. Lead times of 16–26 weeks are normal for springs, drivers and connectors, and stock can vanish.
- Certification is on the path, not after it. In markets like Brazil, nothing with a radio can be sold before homologation, and that includes a small launch batch.
- Design test access before routing: test pads, an RF test strategy and a test mode in firmware.
- Bring-up closes with numbers. Every checklist line records a measured value and the instrument. "Seems fine" does not close a line.
- Keep the roadmap honest. When a gate fails, move the dates and tell the user. Do not shrink later stages to keep the launch date.
References
references/stages.md: what each stage builds, the questions it answers and its gate, plus the critical path, long-lead parts and the iterations to expect.references/bringup-checklist.md: step-by-step board bring-up, from before power to the system soak.references/test-fixtures.md: design for test and the production fixtures, with NRE ranges.templates/stages.example.json: an example plan for a fictional BLE fitness band.templates/roadmap.md: the output template.