Guidewire Migration & Upgrade — Reference
Migration tooling surface, deprecated-API detection, cutover phase definitions, and rehearsal patterns supporting SKILL.md.
Migration Accelerator (Guidewire-supplied tooling)
Guidewire ships a Migration Accelerator (MA) toolkit for on-prem→cloud migrations. Capabilities (subject to per-engagement scoping with Guidewire):
- Schema mapping between on-prem entity model and cloud entity model
- Bulk data transfer with checksum-aware writeback
- Config-package validation against target tenant
- Pre-cutover smoke test scaffolding
MA is engagement-driven (not self-service); engage through the carrier's Guidewire account team. Treat MA as the substrate, not the plan; the migration plan in SKILL.md covers what MA does not (rollback paths, communication, in-flight handling).
Deprecated-API detection
For version upgrades, identify integrations that depend on APIs the target release deprecates. Two complementary techniques:
Static analysis
Grep the integration code for known-deprecated endpoint paths:
# 202403 → 202503 deprecation list (illustrative; consult release notes)
grep -rE "(/v0/|deprecatedEndpoint)" path/to/integration/src/The Guidewire release notes for each version include the deprecation list. Not all deprecations are immediate-removal — some are "deprecated, removed in a later release"; track the removal release for upgrade planning.
Runtime detection
Cloud API responses for deprecated endpoints include a Sunset header (RFC 8594) and a Deprecation header per RFC 8594. Log every response carrying these headers; review weekly:
if (res.headers.get("Deprecation") || res.headers.get("Sunset")) {
log.warn("deprecated-api-call", {
path: req.path,
deprecation: res.headers.get("Deprecation"),
sunset: res.headers.get("Sunset"),
});
}Sunset date in the header is the hard deadline; integration must migrate off before then.
Cutover phase definition (detailed)
Phase 0 — Quiesce (T-2h to T)
Disable non-essential write paths on source. In-flight reads continue. Outbound App Events continue (consumer side will dedup on replay).
# Disable broker portal write paths via maintenance flag
curl -X PATCH $SOURCE/admin/maintenance -d '{"writes": "blocked", "reads": "allowed"}'Phase 1 — Snapshot (T to T+15min)
Capture point-in-time of source database; serves as the migration source-of-truth and as the rollback substrate.
# Source-DB snapshot
pg_basebackup --pgdata=$SNAPSHOT_DIR --wal-method=fetch --label="cutover-$(date -Iseconds)"Phase 2 — Migrate data (T+15min to T+Nh, where N = rehearsed wall-clock)
Bulk transfer with checksum continuation. Per-table parallelism limited to avoid swamping target write capacity.
Phase 3 — Cut integrations (T+Nh to T+Nh+30min)
Repoint every outbound integration to the new tenant's URLs and credentials. Inbound integrations (App Event consumers) re-subscribe to the new messaging destinations.
Phase 4 — Validate (T+Nh+30min to T+Nh+90min)
Smoke tests + 100-policy spot check + 50-claim spot check. Numerical drift threshold pre-defined.
Phase 5 — Open (T+Nh+90min)
Re-enable writes on the new tenant. Source remains read-only.
Phase 6 — Decommission window (T+Nh+90min to T+30 days)
Source remains read-only for regulatory audit access. Decommission only after the audit window closes.
Abort runbooks per phase
Each abort runbook is one page. Same template across phases:
# Abort: Phase N
## Trigger
- <quantitative threshold that fired>
## Steps (~10 minutes)
1. <concrete command>
2. <concrete command>
## Verify recovery
- <metric/query that should return to baseline>
## Communication
- <stakeholder, message, channel>
## Postmortem
- <where the PIR will be filed>Drilled in rehearsal; the team should be able to execute without re-reading.
Schema migration patterns (in-place upgrade)
In-place version upgrades (202403 → 202503) sometimes include database schema changes Guidewire applies during deploy. Two patterns:
| Pattern | When | Behavior |
|---|---|---|
| Online migration | additive changes (new columns, new indexes) | runServer applies during boot; no downtime beyond restart |
| Offline migration | destructive changes (column type change, table rename) | runServer takes the database into maintenance mode; downtime equals migration time |
Release notes specify which version transitions require offline migration. Plan the upgrade window accordingly; offline migration on a large-tenant DB can take hours.
In-flight resource handling
Submissions in Quoted state and claims in Open state cross the cutover boundary. Decision matrix:
| Resource state | Cutover handling |
|---|---|
Submission Draft |
migrate; broker continues editing on new tenant |
Submission Quoted (within validity window) |
migrate; broker can bind on new tenant |
Submission Quoted (validity expired) |
migrate; broker must re-quote on new tenant; communicate the requirement |
Submission Bound (not yet issued) |
migrate; complete issue on new tenant |
Policy In Force |
migrate; live on new tenant |
Claim Open (no in-flight payments) |
migrate; adjuster continues on new tenant |
Claim Open (in-flight payment in PendingApproval) |
complete the payment cycle on source before cutover, OR migrate the pending state and resume on new tenant |
Claim Closed |
migrate; reopen on new tenant if needed |
The "in-flight payment" case is the trickiest; finance team must align with cutover timing.
Parallel-run validation
For high-risk migrations, run the new tenant in parallel with source for 1-2 weeks before cutover. Both systems receive identical traffic; new tenant's writes are discarded; numerical drift is monitored daily.
Cost: doubled cost of running both systems; engineering effort for the dual-write proxy. Benefit: catches subtle reconciliation issues that 100-policy spot checks miss.
Per-state regulatory notification
State insurance regulators may require notification of system migrations. Requirements vary; check NAIC guidance and per-state insurance code for the carrier's licensed states.
| State | Typical requirement |
|---|---|
| NY DFS | 10-day notice for cybersecurity-relevant changes |
| CA DOI | varies by line |
| TX TDI | annual filing covers most changes |
Coordinate with carrier's compliance / legal team. Migration without required notification is a finding waiting to happen.
Upgrade-specific considerations
Gosu language compatibility
Each release may deprecate or remove Gosu language features. Run ./gradlew compileGosu against the target version's gradle plugin; deprecation warnings list every affected location.
Plugin registry compatibility
Some plugin classes are renamed or moved across versions. The plugin/registry/*.xml files reference fully-qualified class names; update per the release notes' plugin migration table.
Sample data compatibility
./gradlew loadSampleData data files may have schema-incompatible entries between versions. Either upgrade the sample data or load fresh sample from the target version's distribution.
Related references
references/implementation-guide.md— extended walkthrough including parallel-run dual-write proxy, Strangler Fig pattern application, blue-green migration tenants- Sibling
guidewire-ci-cd-pipeline/references/API_REFERENCE.md— slot deployment used for the migrated config promotion - Sibling
guidewire-install-auth/references/API_REFERENCE.md— auth setup for the new tenant - Guidewire release notes — authoritative source for deprecation, removal, and schema-change details per version