Launch readiness checklist
Answer each question in writing; link evidence. Mark N/A with a reason.
Architecture and dependencies
- Architecture diagram with request flow, data flow and every dependency.
- For each dependency: SLO, owner, what happens when it is down or slow, timeout and retry settings.
- No single points of failure (or they are documented and accepted).
- Data stores: replication, backups, restore tested (see
sre-data-reliability).
Capacity
- Expected launch traffic and 6–12 month growth estimate (incl. marketing events, client update waves).
- Load test result: per-task and per-cluster capacity, limiting resource.
- Provisioned for peak + loss of largest failure domain (e.g. N+2).
- Quotas reserved with downstream dependencies.
- Autoscaling min/max and signals reviewed; downstream impact of scaling considered.
Failure modes
- Behavior under overload: sheds load / degrades gracefully, doesn't collapse.
- Deadlines set and propagated; retries bounded with backoff + jitter.
- Request criticality defined; batch traffic sheddable.
- Behavior on bad input / corrupt data defined.
- Failover tested.
Client behavior
- Clients back off and jitter; no synchronized polling or wake-ups.
- Mobile/client releases can be throttled or killed server-side.
Processes and automation
- Deploy, rollback, scaling, failover automated.
- Remaining manual procedures documented in runbooks.
- On-call rotation staffed and trained; escalation contacts listed.
Development process
- Code review and CI tests required.
- Release pipeline with canary + control and automated rollback.
- Config changes reviewed, validated and canaried.
External dependencies
- Third-party services: SLA known, fallback defined, contacts listed.
Monitoring and alerting
- SLIs and SLOs documented and agreed.
- Burn-rate alerts configured (page + ticket).
- Golden-signal dashboards; deploys annotated.
- Black-box probes for critical user journeys.
- Every alert has a runbook.
Security, privacy, abuse
- Security review complete.
- Privacy/data-handling review complete.
- Abuse and rate-limiting controls in place.
Rollout plan
- Staged rollout plan with go/no-go criteria per stage.
- Feature flag / kill switch tested.
- Dark launch considered.
- Rollback tested end to end.
- Launch time chosen when the team is available (not before weekends/holidays).
- Communication plan (status page, support team briefed).