Gantt / Roadmap / Timeline Reference (Canvas gantt recipe)

Purpose: Render timeline visuals — gantt charts, release roadmaps, quarterly views — using Mermaid gantt syntax. Canvas draws the picture; the release plan itself lives elsewhere.

Scope Boundary

  • Canvas gantt: Visual rendering of a schedule or roadmap. Inputs are dates, task list, dependencies, milestones.
  • Launch (elsewhere): Owns the release plan, versioning strategy, CHANGELOG, feature flags, rollback plans. Launch decides what ships and when; Canvas shows it.
  • Sherpa (elsewhere): Owns task decomposition into ≤15-min atomic steps; Canvas does not re-plan.

If the ask is "plan the Q3 release and write the CHANGELOG" → Launch. If the ask is "show me Launch's plan as a gantt for the stakeholder deck" → stay in Canvas gantt.

Input Sources

Source Use when Notes
Launch release plan Launch has already authored dates, milestones, release gates Derive verbatim; do not re-estimate
Sherpa task breakdown Project plan exists as atomic steps Aggregate steps into gantt-friendly task blocks (avoid >40 tasks)
Verbal roadmap Leadership sketched Q1–Q4 themes Render as quarterly sections; flag that Launch should formalize
Project tracker export (Linear / Jira / GitHub) Issues have start/due dates Map one epic → one section; one issue → one task

Workflow

UNDERSTAND  →  pick timeline scope: sprint / release / quarter / year
            →  confirm date format (YYYY-MM-DD) and axis unit (day / week / month)
            →  locate authoritative plan: Launch, Sherpa, tracker

ANALYZE     →  extract tasks with start + duration (or start + end)
            →  extract dependencies (task B starts after task A)
            →  extract milestones (point-in-time markers)
            →  mark critical-path tasks

DRAW        →  Mermaid gantt block
            →  group tasks into `section` blocks by team / theme / quarter
            →  use `after <taskId>` for dependencies
            →  use `milestone` markers for release points
            →  use `crit` for critical-path tasks

REVIEW      →  ≤20 tasks per diagram (split by section if over)
            →  axis unit matches timeline scope (weeks for releases, months for quarters)
            →  milestones distinct from tasks
            →  critical path visually obvious
            →  dates verified against source plan

Mermaid Gantt Patterns

Sprint View (2-week scope)

gantt
    title Sprint 42 — Checkout Rewrite
    dateFormat  YYYY-MM-DD
    axisFormat  %m/%d
    section Frontend
    Cart refactor        :active, cart, 2026-04-20, 5d
    Payment form         :pay, after cart, 4d
    section Backend
    Orders API           :crit, api, 2026-04-20, 7d
    Webhook handler      :hook, after api, 3d
    section Milestones
    Feature flag on      :milestone, flag, 2026-05-01, 0d

Quarterly Roadmap

gantt
    title 2026 Product Roadmap
    dateFormat  YYYY-MM-DD
    axisFormat  %b
    section Q1 — Foundation
    Auth rewrite             :auth, 2026-01-06, 8w
    Observability backbone   :obs, 2026-02-03, 6w
    section Q2 — Growth
    Self-serve onboarding    :crit, onb, after auth, 10w
    Billing v2               :bill, 2026-05-01, 9w
    section Q3 — Scale
    Multi-region rollout     :crit, mr, 2026-07-01, 12w
    section Milestones
    GA release               :milestone, ga, 2026-06-30, 0d
    SOC2 audit close         :milestone, soc2, 2026-09-15, 0d

Release Timeline with Dependencies + Critical Path

gantt
    title v2.0 Release
    dateFormat  YYYY-MM-DD
    section Engineering
    API contracts frozen     :done, contracts, 2026-04-01, 2026-04-07
    Backend implementation   :crit, active, be, after contracts, 14d
    Frontend implementation  :fe, after contracts, 18d
    Integration tests        :crit, test, after be, 5d
    section Release Gates
    Staging deploy           :milestone, stg, after test, 0d
    Canary 5%                :milestone, canary, after stg, 0d
    GA                       :milestone, ga, 2026-05-15, 0d

Syntax Notes

  • dateFormat YYYY-MM-DD is the safe default; ISO keeps dates unambiguous across renderers.
  • axisFormat: %m/%d for sprint, %b for quarterly, %Y-%m for yearly.
  • Task states: done (past), active (in progress), crit (critical path) — combinable: crit, active, id, ....
  • milestone tasks take 0d duration and render as a diamond marker.
  • Dependencies: after <taskId> — chain with commas: after a, b waits for both.
  • IDs must be unique per diagram and referenced in after clauses.

Anti-Patterns

  • Rendering a 60-task gantt in one diagram — split by section, per team, or per quarter.
  • Using gantt for pure dependency graphs (no time axis) — use a flowchart instead.
  • Hand-drawn dates that drift from Launch's actual release plan — always cite the source plan and date of sync.
  • Missing critical path — if a release exists, at least one chain must be crit.
  • Milestones with non-zero duration — milestones are point-in-time; use 0d.
  • Quarterly roadmaps with daily axisFormat — mismatched granularity makes the axis unreadable.
  • Re-authoring the CHANGELOG inside the diagram explanation — CHANGELOG is Launch's artifact; link to it.

Handoff

  • From Launch: receive release plan (dates, milestones, gates, rollback windows). Render. Return the Mermaid block with an explicit "rendered from Launch plan as of YYYY-MM-DD" note.
  • To Launch: if rendering reveals date conflicts, missing dependencies, or uncovered critical path, flag and hand back — Canvas does not silently fix plan issues.
  • To Stage: if the gantt is destined for a stakeholder deck, hand off the rendered Mermaid for slide embedding.
  • To Sherpa: if tasks lack decomposition to ≤15-min atomic steps, flag for decomposition before re-rendering.

Output Checklist

  • Timeline scope stated (sprint / release / quarter / year).
  • dateFormat and axisFormat match scope.
  • At least one section grouping.
  • Dependencies use after <id>, not hand-synced dates.
  • Milestones marked with milestone and 0d.
  • Critical path tasks marked crit.
  • ≤20 tasks; split otherwise.
  • Sources cites Launch plan, tracker export, or "informal builder — Launch has not formalized."

Source: SKILL.md on GitHub

No alerts13d5 checks · Risk SAFE
  • Gen Agent Trust Hub13d

    The skill provides comprehensive visualization and reverse-engineering capabilities using Mermaid and other diagramming tools. It possesses a potential attack surface for indirect prompt injection by processing untrusted project code, though it includes best-practice instructions for source disclosure and uncertainty marking. It also documentedly uses well-known external rendering services like Kroki for processing diagram DSL.

  • Socket13d

    No alerts

  • Snyk13d

    Risk: LOW · No issues

  • Runlayer6mo

    14 files scanned · No issues

  • ZeroLeaks5mo

    Score: 93/100 · 2 sections analyzed

Signed by skilld at 35ffd55. This ties the file your Agent reads to that commit on GitHub. It does not review the instructions.

Last checked against GitHub 2 days ago.

Activeupdated 2 weeks ago

README badge

README badge for simota/agent-skills/canvas