Build a phase-gated EOL checklist sized to the sunset, with a named owner on every item. Use when the decision to retire is made and you need the operational plan.

Use this Skill: https://skilld.dev/gh/deanpeters/product-manager-skills/eol-checklist

This session only. Nothing lands on disk.

template.md

≈1.1k tokens on demand. Your agent reads this file only when SKILL.md points to it.

EOL Checklist Template

Fill in the level and phases first, then build only the areas your level warrants. Quality checks at the bottom.

Provenance

Adapted from prompts/eol-checklist.md in the https://github.com/deanpeters/product-manager-prompts repo.


Pick your level first

Level 1 — Light Level 2 — Standard Level 3 — Heavy
Scope Feature, internal tool, API Commercial product, active customers Revenue-critical, hardware, regulated
Phases 2-3 (NSC, EOS, EOL) 4-5 (NSC, EOS, EOE, EOM, EOL) All 6 (NSC through EOSRV)
Areas 4 11 15
Gates Not needed Between major phases Between every phase, with approvers

Most sunsets are Level 2. Insert EOR if contracts run past EOS. Drop EOSRV if there are no service obligations — and say so rather than leaving it blank.

Sticky-note rule: every item is 4-8 words, starts with a verb, and names an owning function.


Template

## EOL Checklist: [Product Name]

**Level**: [1-Light / 2-Standard / 3-Heavy]
**Phases in scope**: [list]
**Phases not in scope**: [list + one-line why]
**Target EOL date**: [date / TBD / Not scheduled]

### Lifecycle Phase Definitions (include only phases in scope)

- **NSC (Notice of Status Change)**: Decision communicated; planning begins
- **EOS (End of Sale)**: No new customers can purchase
- **EOE (End of Expansion)**: Existing customers cannot add capacity
- **EOR (End of Renewal)**: Existing contracts will not be renewed
- **EOM (End of Maintenance)**: Bug fixes and patches stop
- **EOL (End of Life)**: Product is fully retired
- **EOSRV (End of Service)**: Support and service obligations end

---

### Phase: [Name] -- Target Date: [date / TBD / Not scheduled]

(Repeat per phase. Include only the areas your level warrants.)

#### Product and Strategy (L1+)
- [ ] [Verb-first item, 4-8 words] -- Owner: [function]

#### Engineering and Technical (L1+)
- [ ] [Item] -- Owner: [function]

#### Support (L1+)
- [ ] [Item] -- Owner: [function]

#### Documentation and Training (L1+)
- [ ] [Item] -- Owner: [function]

#### Legal and Contractual (L2+)
- [ ] [Item] -- Owner: [function]

#### Financial Planning (L2+)
- [ ] [Item] -- Owner: [function]

#### Sales (L2+)
- [ ] [Item] -- Owner: [function]

#### Marketing (L2+)
- [ ] [Item] -- Owner: [function]

#### Customer Success (L2+)
- [ ] [Item] -- Owner: [function]

#### IT Systems (L2+)
- [ ] [Item] -- Owner: [function]

#### Data Management (L2+)
- [ ] [Item] -- Owner: [function]

#### Inventory and Supply Chain (L3)
- [ ] [Item] -- Owner: [function]

#### Channel and Partner Management (L3)
- [ ] [Item] -- Owner: [function]

#### Regulatory and Compliance (L3)
- [ ] [Item] -- Owner: [function]

#### Internal Organizational Alignment (L3)
- [ ] [Item] -- Owner: [function]

---

### Phase Gate Criteria (L2+)

#### [Phase A] to [Phase B]
- [ ] [What must be true] -- Approver: [role]
- [ ] [What must be true] -- Approver: [role]

---

### Post-EOL Actions (all levels)

- [ ] [Archive artifacts and records] -- Owner: [function]
- [ ] [Run lessons-learned review] -- Owner: [function]
- [ ] [Publish final report] -- Owner: [function]

### Assumptions to Validate
- [Assumption 1]
- [Assumption 2]
- [Assumption 3]

Quality checks

Any "no" is a rewrite, not a nitpick.

Proportion

  • Level was chosen deliberately, not defaulted to the heaviest
  • Phases out of scope are listed with a one-line reason
  • If you went lighter than recommended, you know which area dropped out

Item hygiene

  • Every item is 4-8 words and starts with a verb
  • Every item names an owning function — no blanks, no "the team"
  • Each item sits in the phase where the work happens, not where it's announced

The four things sunsets strand

  • Data — export format, availability window, deletion schedule
  • Contracts — renewal language, SLA terms, refunds or credits owed
  • Access — API keys, integrations, SSO, downstream readers
  • Money — forecast adjustment, rev-rec treatment, cost of the sunset itself

Gates

  • Every gate names an approver (no approver = not a real gate)
  • Gates state conditions that must be true, not dates that must pass

Dates

  • No date was invented to fill a blank
  • Any Not scheduled entry is paired with the precondition to schedule it

Closure

  • A lessons-learned review is on the list and owned
  • Assumptions are stated plainly rather than silently resolved

Source: SKILL.md on GitHub

No alerts1mo3 checks · Risk SAFE
  • Gen Agent Trust Hub1mo

    This skill helps product managers create structured End-of-Life (EOL) checklists by providing phase-gated templates and examples. It is a text-based guidance skill and contains no security risks or malicious code.

  • Socket1mo

    No alerts

  • Snyk1mo

    Risk: LOW · No issues

Signed by skilld at d025768. This ties the file your Agent reads to that commit on GitHub. It does not review the instructions.

Last checked against GitHub last month.

Activeupdated 2 months ago
argument-hint
[product being sunset, and any hard dates]
type
component
theme
eol-transition
Other metadata
intent
Generate a phase-gated EOL checklist tailored to the complexity of the sunset. Covers up to 15 functional areas across the lifecycle gates, but right-sizes the output so a minor feature deprecation gets a short punch list while a flagship product retirement gets the full cross-functional playbook. Every item names a verb and an owner.
best_for
[
  "Turning a sunset decision into an operational plan with owners and dates",
  "Making sure a retirement doesn't strand data, contracts, or inventory",
  "Right-sizing process so a feature deprecation doesn't get a flagship playbook"
]
scenarios
[
  "We've decided to retire the legacy module in December — what actually has to happen between now and then?",
  "Hardware line with channel partners and service contracts; I need the full cross-functional checklist"
]
estimated_time
20-40 min

README badge

README badge for deanpeters/product-manager-skills/eol-checklist