Build a launch plan sized by tier: owners, dates, go/no-go criteria, and a readiness scorecard. Use when a launch needs every function ready at once and nobody has defined 'ready'.

Use this Skill: https://skilld.dev/gh/deanpeters/product-manager-skills/launch-plan

Nothing lands on disk. Nothing to clean up.

Fork this Skill

Edit a local copy. It keeps the author and licence.

examplessample-industrial.md

≈1.2k tokens on demand. Your agent reads this file only when SKILL.md points to it.

Launch Plan Example: Industrial (Tier 1)

Offering: NFA-500 retrofit controller (Northfield Automation), successor to the NFA-200 Fixed date: Trade fair, April 21 Context: New hardware generation, 8 channel partners, ~120 installed NFA-200 sites that will migrate over years, UL and CE certification, a mounting bracket that differs from the NFA-200. This is the launch that follows the NFA-200 retirement thread.

Why this example exists: the SaaS example collapses four dates into one. Here they pull apart by nine months, and the gap between them is the plan.


## Launch Plan: NFA-500 Retrofit Controller

### 1. Tier assessment
| Criterion | Rating | Reason |
|---|---|---|
| Revenue and margin at stake | High | Successor to the base product line [FROM YOU] |
| Newness to the customer | Medium | Same job, new bracket and commissioning steps |
| Newness to the company | Medium | First controller with a connected-service tier |
| Regulatory and safety exposure | High | UL 508A re-evaluation; CE conformity for the new radio module |
| Installed-base impact | High | ~120 NFA-200 sites; every migration is a scoped site visit |
| Channel impact | High | Partners must stock a new bracket and learn new commissioning |

**Proposed tier:** 1 Full. Why: four High scores.
**A lighter tier would leave uncovered:** formal gates, partner stocking plan, spare parts coverage.

### 2. Four dates
| Moment | Date | Gap and why |
|---|---|---|
| Announce | Apr 21 (trade fair) | |
| Order opens | Jul 1 | 10 weeks: partners need price files and bracket stock; NFA-200 orders continue meanwhile |
| First delivery | Oct 15 | 15 weeks: certification and first-article build on the critical path |
| Full support | Jan 20 | 13 weeks: technician training and spares in all launch countries |

**Announce-to-deliver gap is 6 months.** Sales plan for NFA-200 deals during the gap: continue
selling, with a migration path and a price-protection clause. Owner: Sales director.

### 3. Checklist (selected rows)
| Function | Deliverable | Owner | Due | Status |
|---|---|---|---|---|
| Certification | UL 508A evaluation complete; EU declaration of conformity signed | Compliance lead | Sep 15 | At risk |
| Channel | 8 partners briefed under NDA; price files sent; bracket stock plan agreed | Channel manager | Jun 1 | On track |
| Service and spares | 40 technicians trained; spares for first 12 months of planned installed base stocked | Service director | Jan 5 | Not started `[NEEDS SOURCE]` |
| Production | Ramp plan sized to *realistic* forecast; first-article inspection passed | Plant manager | Sep 30 | On track |
| Documentation | Manuals and safety instructions in 5 languages | Tech publications | Sep 1 | At risk |
| Pricing | List price, discount bands, partner margin approved | Commercial lead | May 15 | On track |
| Marketing | Fair booth, live demo unit, data sheet | Marketing manager | Apr 1 | On track |

### 4. Go/no-go criteria (written Feb 10)
| # | Check | Threshold | Evidence | Owner | Type |
|---|---|---|---|---|---|
| 1 | Declaration of conformity | Signed for all launch countries | Document | Compliance | Must-pass (Gate 2) |
| 2 | Technicians trained | 40 of 40 in launch countries | Records | Service | Must-pass (Gate 2) |
| 3 | Spares stocked | 12 months of planned installed base | Warehouse report | Service | Must-pass (Gate 2) |
| 4 | Capacity | Ramp confirmed vs realistic forecast | Plan sign-off | Plant | Must-pass (Gate 1) |
| 5 | Translated manuals | 5 languages | Release | Tech pubs | Watch |

**Gate 1 (before order intake, Jul 1):** Approver: COO. **Gate 2 (before first shipment, Oct 15):** Approver: COO.

### 7. Premortem (excerpt)
| Failure story | Cause | L/I | Landed as |
|---|---|---|---|
| "First three sites were commissioned by partner crews we hadn't trained; two failed acceptance" | Training scheduled after first shipment | High/High | Partner crew training added to Gate 2 as must-pass criterion 2 |
| "A customer waited 5 weeks for a bracket" | Spares counted controllers, not brackets | Med/High | Criterion 3 rewritten to include brackets |

### Riskiest assumptions
1. Certification lead time is a planning estimate, not a quote from the assessment body.
2. Spares quantity depends on a migration forecast nobody has validated.

What to learn from this

  • Three of five go/no-go criteria are Service's, not Engineering's. That is typical, and it is why Service is on the forum.
  • The announce-to-deliver gap is a decision with an owner. Without one, NFA-200 sales quietly stall for six months.
  • Premortem stories rewrote two criteria. Brackets were nowhere on the original spares list.

Source: SKILL.md on GitHub

No rule matched.

skilld matched fixed text patterns in SKILL.md and file names. Patterns miss obfuscated code.

skilld run checks every file with the same patterns. It asks for approval before it loads a Skill with a behavior marked Needs approval.

1 warning7d3 checks · Risk SAFE
  • Gen Agent Trust Hub7d

    The skill is a set of documentation and templates for creating product launch plans. It contains no executable code, network operations, or sensitive data access, and functions solely as a guided text-based workflow.

  • Socket7d

    No alerts

  • Snyk7d

    Risk: MEDIUM · 1 issue

Signed by skilld at 476ae12. This ties the file your Agent reads to that commit on GitHub. It does not review the instructions.

Last checked against GitHub last week.

Activeupdated last week
argument-hint
[what is launching, and the date that drives it]
type
workflow
theme
strategy-positioning
Other metadata
intent
Make a launch a coordinated business event instead of a ship date, so every function that touches the customer is ready, the effort fits the size of the launch, and the go/no-go call is made on criteria the team agreed before anyone saw the status. Right-sized so a minor variant gets a short punch list and a platform launch gets the full cross-functional plan.
best_for
[
  "Planning a launch across Sales, Support or Service, Marketing, Legal, and Operations",
  "Deciding how much launch effort an offering deserves before the work starts",
  "Writing go/no-go criteria before the gate, not after the status is known",
  "Reviewing a launch plan for the function everyone forgot"
]
scenarios
[
  "We launch the route optimizer in six weeks and Support has not seen it yet. Build the plan",
  "Is this a Tier 1 or Tier 2 launch, and what does each function owe us?",
  "Review our launch plan. I think we forgot the distributors and the spare parts",
  "Help me write go/no-go criteria for a hardware launch with a trade-fair date"
]
estimated_time
30-60 min to plan; weeks to execute