Build a launch plan sized by tier: owners, dates, go/no-go criteria, and a readiness scorecard. Use when a launch needs every function ready at once and nobody has defined 'ready'.

Use this Skill: https://skilld.dev/gh/deanpeters/product-manager-skills/launch-plan

Nothing lands on disk. Nothing to clean up.

Fork this Skill

Edit a local copy. It keeps the author and licence.

examplessample.md

≈1.1k tokens on demand. Your agent reads this file only when SKILL.md points to it.

Launch Plan Example: SaaS (Tier 2)

Offering: Route Optimizer, a new module in Fieldlight (field service SaaS) Fixed date: General availability June 12 (the customer conference keynote) Context: Existing customers, existing channels, a new add-on price. Product leadership is excited. Support has not seen it. This is the plan a PM builds in one sitting, once the tier is agreed.

Why this example exists: it shows a Tier 2 plan where the work is not engineering. Four of the eight functions hold rows the build schedule never mentioned.


## Launch Plan: Route Optimizer

### 1. Tier assessment
| Criterion | Rating | Reason |
|---|---|---|
| Revenue and margin at stake | Medium | Add-on priced at a share of seat price; ~15% attach in year 1 [FROM YOU] |
| Newness to the customer | Medium | New capability, same users |
| Newness to the company | Low | Same channel, same billing |
| Regulatory and safety exposure | Medium | Uses technician GPS traces: privacy review needed |
| Installed-base impact | Low | Optional, off by default |
| Channel impact | Low | Resellers sell add-ons already |

**Proposed tier:** 2 Standard. Why: one new exposure (location data), nothing else new.
**A lighter tier would leave uncovered:** privacy review and reseller briefing.
**Confirmed by:** Launch forum, May 5

### 2. Four dates
| Moment | Date | Gap |
|---|---|---|
| Announce | Jun 12 (keynote) | 0 days to GA by design |
| Order opens | Jun 12 | Reseller price file due May 29 |
| First delivery | Jun 12 (tenants enabled on request) | Self-serve on Jul 8 |
| Full support | Jun 12 for tier-1 help; Jul 8 for advanced routing issues | 26-day gap accepted: advanced issues escalate to a named engineer |

### 3. Checklist (selected rows)
| Function | Deliverable | Owner | Due | Status |
|---|---|---|---|---|
| Support | 12 agents complete a 90-minute session and pass 5 sample tickets | Dana (Support lead) | Jun 2 | At risk [FROM YOU] |
| Support | Runbook and escalation path live in help center | Dana | Jun 5 | On track |
| Sales and channel | Resellers briefed; price file sent | Marco (Channel) | May 29 | On track |
| Legal | Privacy review of GPS trace use closed; DPA addendum text approved | Priya (Legal) | May 22 | Not started `[NEEDS SOURCE]` |
| Pricing | Add-on SKU, billing plan, quote template live | Lee (RevOps) | Jun 1 | On track |
| Marketing | Keynote demo script, data sheet, web page | Sam (PMM) | Jun 8 | On track |
| Operations | Routing service load-tested to 3x projected day-one traffic | Ravi (Eng lead) | May 30 | `[AI-SUGGESTED, VALIDATE THIS]` |
| Internal | Customer success has the FAQ and a rollback script | Jo (CS lead) | Jun 5 | Not started |

### 4. Go/no-go criteria (written May 5)
| # | Check | Threshold | Evidence | Owner | Type |
|---|---|---|---|---|---|
| 1 | Privacy review | Closed, addendum published | Legal sign-off | Priya | Must-pass |
| 2 | Support readiness | All tier-1 agents certified | Roster | Dana | Must-pass |
| 3 | Load test | 3x day-one traffic, error rate under threshold `[NEEDS SOURCE]` | Test report | Ravi | Must-pass |
| 4 | Reseller price file | Delivered | Sent receipt | Marco | Watch |
| 5 | Demo reliability | 3 clean runs on conference network | Rehearsal log | Sam | Watch |

**Gate:** Jun 5. Approver: VP Product (one person). DACI: Driver PM; Contributors function owners.

### 7. Premortem (excerpt)
| Failure story | Cause | L/I | Landed as |
|---|---|---|---|
| "The keynote demo timed out and Support got 200 tickets we couldn't answer" | Demo env not load-tested; agents untrained | High/High | Criteria 2 and 3 (added) |
| "A customer's counsel asked how we store technician locations" | Privacy review slipped behind the keynote | Med/High | Criterion 1 (promoted to must-pass) |

### Riskiest assumptions
1. Load test threshold is `[NEEDS SOURCE]`: if it is set too low, criterion 3 passes and it fails live.
2. The 26-day support gap assumes advanced issues are rare. Nobody has measured that.

What to learn from this

  • The build was done in April. Every open row is a business function. That is the whole lesson of "a launch is not a ship date."
  • The premortem changed the plan twice. Privacy review moved from "nice to have" to must-pass, because a function owner (Legal) wrote the failure story, not the PM.
  • The 26-day support gap is a decision, written down, with a named engineer on escalation. It is not an accident someone discovers in July.

Source: SKILL.md on GitHub

No rule matched.

skilld matched fixed text patterns in SKILL.md and file names. Patterns miss obfuscated code.

skilld run checks every file with the same patterns. It asks for approval before it loads a Skill with a behavior marked Needs approval.

1 warning7d3 checks · Risk SAFE
  • Gen Agent Trust Hub7d

    The skill is a set of documentation and templates for creating product launch plans. It contains no executable code, network operations, or sensitive data access, and functions solely as a guided text-based workflow.

  • Socket7d

    No alerts

  • Snyk7d

    Risk: MEDIUM · 1 issue

Signed by skilld at 476ae12. This ties the file your Agent reads to that commit on GitHub. It does not review the instructions.

Last checked against GitHub last week.

Activeupdated last week
argument-hint
[what is launching, and the date that drives it]
type
workflow
theme
strategy-positioning
Other metadata
intent
Make a launch a coordinated business event instead of a ship date, so every function that touches the customer is ready, the effort fits the size of the launch, and the go/no-go call is made on criteria the team agreed before anyone saw the status. Right-sized so a minor variant gets a short punch list and a platform launch gets the full cross-functional plan.
best_for
[
  "Planning a launch across Sales, Support or Service, Marketing, Legal, and Operations",
  "Deciding how much launch effort an offering deserves before the work starts",
  "Writing go/no-go criteria before the gate, not after the status is known",
  "Reviewing a launch plan for the function everyone forgot"
]
scenarios
[
  "We launch the route optimizer in six weeks and Support has not seen it yet. Build the plan",
  "Is this a Tier 1 or Tier 2 launch, and what does each function owe us?",
  "Review our launch plan. I think we forgot the distributors and the spare parts",
  "Help me write go/no-go criteria for a hardware launch with a trade-fair date"
]